Concept: Some project topologies degrade the reliability of ES metrics early in a project’s timeline. ES Longest Path (ES-LP) alleviates the difficulty.
Practice: Pioneering research by Mario Vanhoucke and Stephan Vandevoorde (2007) demonstrated that Earned Schedule metrics outperform, on average, more traditional Earned Value-based metrics. The researchers used innovative simulation techniques to establish the superiority of Earned Schedule for predictions of final duration.
The researchers then extended their simulation scenarios to cover specific schedule configurations. Although the initial study was widely accepted, the follow-up studies have been challenged. A summary of the controversy follows. For details, see my posts in January 2016.
In one follow-up study, Vanhoucke and Vandevoorde (2008) purported to test ES reliability for critical and non-critical activities. They concluded that discrepancies between performance of critical and non-critical activities undermine the reliability of ES duration forecasts.
Walt Lipke (2014a) disputed the claim. In Lipke’s view, Vanhoucke and Vandevoorde’s simulations were unrealistic. They failed to reflect the inter-dependency between critical and non-critical tasks. Furthermore, they ignored the fact that, at the end of a project, the SPIt converges to a value that ensures the EACt equals the real duration of the project.
In a second follow-up study, Vanhoucke and Vandevoorde (2009) examined the impact of project topology on the reliability of EVM metrics. The researchers used the term “project topology” as follows:
The topological structure of a network is defined by the distribution of the activities in the network and the precedence relations between these activities. (Ibid, p 26)
A single topological indicator, serial vs. parallel activities (SP), was the focus of the research. The SP indicator measures where the project’s network lies on a scale between 100% serial activities and 100% parallel activities. Crucially, Vanhoucke and Vandevoorde tied SP to the critical/non-critical distinction of the first follow-up study:
[SP is] a measure for the amount of critical and non-critical activities in a network. (Ibid, p 27)
The researchers concluded that EVM metrics, including ES, do better in serial networks.
A more serial network contains, on average, more critical activities, which results in a better forecast accuracy compared to more parallel networks. (Ibid, p 29)
As shown in Diagrams 1a and 1b, ES duration forecasts suffered less than other EVM forecasts. But, according to their study, ES forecasts still suffered.
Because Vanhoucke and Vandevoorde tied SP to critical/non-critical scenarios, the second follow-up study is subject to the same objections raised to the first one. Again, the objections have been detailed in previous posts.
Still, for several reasons, the study was beneficial. First, it prompted further research on how project topology affects ES metrics. Walt Lipke (2014b) constructed scenarios that avoided the problems faced by Vanhoucke and Vandevoorde. Lipke tested his scenarios on 16 actual projects and found that ES metrics perform better as projects progress.
Diagram 2 shows the results from Lipke’s tests. The number of problems shrinks from a maximum of 40% at the start to 0% at the end of the projects in his study.
Diagram 2
Second, the simulations remain instructive about early parts of projects. Why? Because it is primarily later stages of the simulations that fail to reflect the convergence characteristic of ES. That’s where convergence should happen. Thus, evidence of forecasting problems early in projects remains relatively unimpeached.
For the same reason, Vanhoucke and Vandevoorde’s conclusion about serial projects (or serial parts of projects) remains intact: serial activities engender more accurate ES forecasts than do parallel ones. Lipke’s research bolsters the point. Diagram 2 shows a decline in discrepancies as the projects progress. Assuming that later stages of projects are more serial than early ones, it follows that ES forecasts become more reliable as schedules becomes more serial.
In conclusion, research shows that project topology affects the reliability of ES forecasts. They are more reliable later in projects when activities are more likely to be serial. An extension to ES leverages these insights and virtually eliminates ES reliability problems.
References
Lipke, W. (2012). Speculations on Project Duration Forecasting. The Measurable News, III, 1, 4-7.
Lipke, W. (2014a). Examining Project Duration Forecasting Reliability. PM World Journal, III (III).
Lipke, W. (2014b). Testing Earned Schedule Forecasting Reliability. PM World Journal, III (VII).
Lipke, W. (2015). Applying Statistical Forecasting of Project Duration to Earned Schedule-Longest Path. The Measurable News, II, 31-38.
Vanhoucke, M., & Vandevoorde, S. (2008). Earned Value Forecast Accuracy and Activity Criticality. The Measurable News, Summer, 13-16.
Vanhoucke, M., & Vandevoorde, S. (2009). Forecasting a Project’s Duration under Various Topological Structures. The Measurable News, Spring, 26-30.
|